TxDOT is alerting drivers to a closure on Interstate 30. The eastbound entrance ramps from Collins Street and Nolan Ryan Expressway will both be closed Sept. 28 and 29 from 9 a.m. until 3 p.m. Drivers will be detoured to the entrance ramp at Copeland Road.
A complete list of openings and closures is below with new additions in bold.
Click here to learn more about the I-30/SH 360 Interchange Project.
I-30 Mainlanes and Ramps
I-30 Westbound Mainlanes
- Through summer 2020: The right, outside auxiliary lane between Great Southwest Parkway to 0.2 miles east of Six Flags Drive exit ramp is closed for construction of new westbound exit ramp to Six Flags Drive.
I-30 Eastbound Entrance from Collins Street
- Daily, Sept. 28-29, 9 a.m. -3 p.m.: The I-30 eastbound entrance from Collins Street will be closed for sign construction. Traffic will be detoured to the next available entrance ramp from Copeland Road near SH 360.
I-30 Eastbound Entrance from Nolan Ryan Expressway
- Daily, Sept. 28-29, 9 a.m.-3 p.m.: The I-30 eastbound entrance from Nolan Ryan Expressway will be closed for sign construction. Traffic will be detoured to the next available entrance ramp from Copeland Road near SH 360.
I-30 Eastbound Exit to SH 360 Southbound
- This direct connector ramp is now in service
I-30 Westbound Exit to SH 360/Six Flags Drive
- A new I-30 westbound exit ramp to SH 360/Six Flags Drive is now open to traffic, replacing the existing loop exit ramp. Traffic makes a left turn through a signalized intersection to continue across I-30 towards SH 360. BE AWARE OF NEW TRAFFIC PATTERN.
I-30 Westbound Entrance from SH 360/Six Flags Drive
- A new traffic signal is active at the intersection with the new, permanent I-30 westbound exit ramp to SH 360/Six Flags Dr. Traffic passes through this signalized intersection to access the westbound I-30 entrance ramp. BE AWARE OF NEW TRAFFIC PATTERN.
I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection
- PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.
I-30 Eastbound Entrance from Northbound Ballpark Way
- PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road
I-30 Eastbound Frontage Road Between Convention Center Drive/Ballpark Way Northbound Ramp
- Continuous, Sept. 28, 8 a.m. - Oct. 19, 3 p.m.: The I-30 eastbound frontage road between Convention Center Drive and the Ballpark Way northbound ramp will be closed. Traffic will be detoured south on Convention Center Drive to reach Ballpark Way.
I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)
Westbound I-30 HOV lane west of SH 161
- Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.
Eastbound I-30 HOV lane between Center Street and Duncan Perry Road
- Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.
SH 360 Mainlanes and Ramps
SH 360 Southbound Mainlanes
- Sept. 30, 9 a.m.-3 p.m.: The left, inside lane of SH 360 southbound mainlanes will be closed between Randol Mill Road and Division Street to place temporary concrete traffic safety barrier.
- Overnight, Oct. 16, 7 p.m.-6 a.m.: The left, inside lane of SH 360 southbound mainlanes will be closed between Division Street and Mitchell Street for bridge work.
- Continuously through Oct. 31: SH 360 southbound mainlanes will be reduced to two lanes between Avenue J and Six Flags Drive for median utility work. EXPECT DELAYS.
- Daily through Oct. 31, 9 a.m.-3 p.m. (excluding Sundays and holiday blackouts): SH 360 southbound mainlanes will have various lanes closed between Division Street and Kingswood Boulevard to complete various work.
SH 360 Northbound Mainlanes
- Sept. 30, 9 a.m. - 3 p.m.: The left, inside lane of SH 360 northbound mainlanes will be closed between Division Street and Randol Mill Road to place temporary concrete traffic safety barrier.
- Nightly, Sept. 29-Oct .1, 7 p.m. - 6 a.m.: The left, inside lane of SH 360 northbound mainlanes will be closed between Park Row Drive and Abram Street for median paving.
- Continuously, Oct. 2-5, Oct. 9-12, Oct. 16-19, Oct. 23-26, 7 p.m. - 6 a.m.: The left, inside lane of SH 360 northbound mainlanes will be closed between Park Row Drive and Division Street for paving operations.
- Continuously through Oct. 2: The left, inside lane of SH 360 northbound mainlanes will be closed continuously between Avenue J and Brown Boulevard/Avenue K for overhead structure work.
- Daily through Oct. 31, 9 a.m.-3 p.m. (excluding Sundays and holiday blackouts): SH 360 northbound mainlanes will have various lanes closed between Kingswood Boulevard and Division Street to complete various work.
SH 360 Southbound Exit to Avenue J/Lamar Boulevard/Six Flags Drive
- Daily through Oct. 9, 9 a.m. -3 p.m. (excluding Saturdays and Sundays): The SH 360 southbound exit to Avenue J/Lamar Boulevard/Six Flags Drive will be closed for wall construction. Traffic will be directed to the prior exit to Brown Boulevard/Avenue K.
SH 360 Southbound Exit to I-30 Westbound
- This direct connector ramp is now in service.
SH 360 Southbound Entrance from Brown Boulevard/Avenue K
- PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.
SH 360 Southbound Exit to Lamar Boulevard
- PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.
SH 360 Southbound Entrance from Lamar Boulevard
- PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.
SH 360 Frontage Road
SH 360 Southbound Frontage Road
Avenue K to Avenue J
- Through Oct. 15: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.
SH 360 South-to-North U-turn at Lamar Boulevard
- The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.
SH 360 South-to-North U-turn at Six Flags Drive
- The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.
SH 360 South-to-North U-Turn at Abram Street
- Continuously through Oct. 31: The SH 360 south-to-north U-turn at Abram Street will be closed for SH 360 bridge work.
SH 360 Northbound Frontage Road
Billy B Avenue to Donald Terrace
- Continuously through Oct. 31: The left, inside lane of SH 360 northbound frontage road between Billy B Avenue and Donald Terrace is closed.
Randol Mill Road to Avenue E
- Continuous through Dec. 15: The SH 360 northbound frontage road between Randol Mill Road and Avenue E will be reduced to one lane for underground utility work.
SH 360 North-to-South U-Turn at Abram Street
- Continuously through Oct. 31: The SH 360 north-to-south U-turn at Abram Street will be closed for SH 360 bridgework.
SH 360 North-to-South U-turn at Six Flags Drive
- The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.
SH 360 North-to-South U-turn at Lamar Boulevard
- The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.
Local Streets
Avenue F
- Through winter 2020, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.
Copeland Road
- PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
- PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.
Majesty Drive
- Continuously through Oct. 31: The SH 360 northbound frontage road intersection with Majesty Drive will be closed for utility work. Traffic will be detoured east on Glenn Drive and north on 106th Street to reach Majesty Drive.
Glenn Drive
- Continuously through Oct. 31: The SH 360 northbound frontage road intersection with Glenn Drive will be closed for utility work. Traffic will be detoured east on Randol Mill Road, and north on 106th St to reach Glenn Drive.
Convention Center Drive/Copeland Road Intersection
- PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.
105th Street
- PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.
Abram Street
- Daily through Oct. 31, 9 a.m.-3 p.m.: Eastbound and westbound Abram Street between frontage road intersections will be closed for bridge work. Westbound traffic will be detoured north on the frontage road to cross SH 360 at Division Street and return via the southbound frontage road. Eastbound traffic will be detoured south on the frontage road to cross SH 360 at Mitchell Street and return via the northbound frontage road.
- Overnight, Oct. 9 and Oct 16., 7 p.m.-6 a.m.: Eastbound and westbound Abram Street under SH 360 and the SH 360 frontage roads will be closed for bridge work. Westbound traffic will be detoured north on the frontage road to cross SH 360 at Division Street and return via the southbound frontage road. Eastbound traffic will be detoured south on the frontage road to cross SH 360 at Mitchell Street and return via the northbound frontage road.
Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects