Daytime Lane Closures Underway on Abram Street, Mayfield Road
By Office of Communication
Posted on March 09, 2020, March 09, 2020

30-360 project

If you drive Abram Street or Mayfield Road under SH 360, prepare for daytime lane closures. TxDOT will close various lanes of both roads, in both directions, under SH 360 this week. The closures will last from 9 a.m. until 3 p.m. through March 20. 

A complete list of closures is below with new additions in bold.

Click here to learn more about the I-30/SH 360 Interchange Project.

I-30 Mainlanes and Ramps

I-30 Eastbound Entrance from Copeland Road

  • Through fall 2020: A temporary eastbound I-30 entrance ramp will be opened and accessible from Copeland Road between Ballpark Way and SH 360.

I-30 Eastbound Entrance from Convention Center Dr/Copeland Road Intersection 

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road

I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center St and Duncan Perry Road

  • Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlaines and Ramps

SH 360 Southbound Mainlanes

  • Daily through March 13, 9 a.m.-5 p.m.: The left, inside lane of southbound SH 360 mainlanes between Division Street and Kingswood Boulevard will be closed for truck access to the median.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard 

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Frontage Road

SH 360 Southbound Frontage Road

Avenue K to Avenue J

  • Through summer 2020: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.

Mitchell Street to Reever Street

  • Continuously through March 31: The left, inside lane of the SH 360 southbound frontage road between Mitchell Street and Reever Street will be closed for sound wall construction.

SH 360 South-to-North U-turn at Lamar Boulevard

  • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Six Flags Drive

  • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 Northbound Frontage Road

Pioneer Parkway to Donald Terrace

  • Daily through March 31, 9 a.m.-3 p.m.: The right shoulder and outside lane of SH 360 northbound frontage road between Pioneer Parkway and Donald Terrace will be closed for sound wall construction. 

Mitchell Street to Abram Street

  • Daily, through March 31, 9 a.m.-3 p.m.: The left lane of SH 360 northbound frontage road between Mitchell Street and Abram Street will be closed to construct a sound wall. 

Glenn Drive to Avenue E

  • Continuously through March 31: The SH 360 northbound frontage road between Glenn Drive and Avenue E will be reduced to one lane for underground utility work.

SH 360 North-to-South U-turn at Six Flags Drive

  • The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Lamar Boulevard

  • The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

Local Streets

I-30 Entrance from Ballpark Way

  • PERMANENT: The northbound Ballpark Way ramp to eastbound I-30 will be closed for reconstruction to connect with Copeland Road. Northbound Ballpark Way traffic may exit to Copeland Road, turn right and enter on a temporary eastbound I-30 entrance ramp.

Avenue F

  • Through winter 2020, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

Copeland Road

  • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
  • PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

105th Street

  • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.

Abram Street

  • Daily through March 20, 9 a.m.-3 p.m.: Various lanes of eastbound and westbound Abram Street will be closed under SH 360 for bridge work.

Mayfield Road

  • Daily through March 20, 9 a.m.-3 p.m.: Various lanes of eastbound and westbound Mayfield Road will be closed under SH 360 for bridge work

Six Flags Drive

  • Nightly through March 14, 11 p.m.-5 a.m.: Eastbound and westbound Six Flag Drive at SH 360 will be closed for bridge construction. Westbound traffic will be detoured north to cross under SH 360 at Lamar Boulevard and return via the SH 360 southbound frontage road. Eastbound traffic will be detoured south to cross under SH 360 at Randol Mill Road and return via the SH 360 northbound frontage road.
Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects
News, Headlines, Streets