Evening Lane Closures Planned on I-30 This Week
By Office of Communication
Posted on April 19, 2021, April 19, 2021

I-30 Detour Map

TxDOT is alerting drivers to expect delays on Interstate 30 this week. 

The westbound mainlanes will be reduced to one lane April 19 and 20 from 8 p.m. until 5 a.m. the next morning between Great Southwest Parkway and Ballpark Way for bridge construction. The eastbound mainlanes will be reduced to one lane through this same stretch April 21 beginning at 8 p.m. All eastbound lanes should reopen by 5 a.m. the next morning. 

The work is part of the $233 million Interstate 30/SH 360 Interchange Project and the SH 360 Widening Project. Closures are subject to changes due to weather and schedule. For more information, please visit the Keep 30360 Moving website.

 New or updated items are indicated in bold.

 The City of Arlington has partnered with Waze to give drivers the best experience possible to get around town. Drivers can download Waze for free at www.waze.com/get for iOS and Android and see real-time traffic, find optimal routes, avoid road closures and more.

Weekly Lane Closure Look Ahead

Closures are subject to changes due to weather and schedule. Below are anticipated traffic impacts for the coming weeks.

Click here to learn more about the I-30/SH 360 Interchange Project.

I-30 Mainlanes and Ramps 

I-30 Westbound Mainlanes

  • Daily, April 19-24, 9 a.m. - 3 p.m.: The left, inside lane of I-30 westbound mainlanes will be closed between Six Flags Drive and Ballpark Way for bridge construction.
  • Nightly, April 19-20, 8 p.m. - 5 a.m.: I-30 westbound mainlanes will be reduced to one lane between Great Southwest Parkway to Ballpark Way for bridge construction. EXPECT DELAYS.

I-30 Eastbound Mainlanes

  • Daily, April 19-24, 9 a.m. - 3 p.m.: The left, inside lane of I-30 eastbound mainlanes will be closed between Ballpark Way and Six Flags Drive for bridge construction.
  • Overnight, April 21, 8 p.m. - 5 a.m.: The I-30 eastbound mainlanes will be reduced to one lane between Ballpark Way and Great Southwest Parkway for bridge construction. EXPECT DELAYS.

 I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road

I-30 Westbound Exit to SH 360/Six Flags Drive

  • Nightly, April 19-20, 8 p.m. - 5 a.m.: The I-30 westbound exit to SH 360/Six Flags Drive will be closed for bridge construction. Traffic will be detoured to the next exit to Ballpark Way, turn north on Ballpark Way, then an immediate right on eastbound Lamar Boulevard to access SH 360.

I-30 Westbound Entrance from SH 360/Six Flags Drive

  • Nightly, April 20-21, 8 p.m. - 5 a.m.: The I-30 westbound entrance from SH 360/Six Flags Drive will be closed for bridge construction. Traffic will be detoured east to SH 161, cross I-30, and return on the I-30 westbound mainlanes.

I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center Street and Duncan Perry Road

  • Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlanes and Ramps

SH 360 Southbound Mainlanes

  • Continuously through Fall 2021: SH 360 southbound mainlanes will be reduced to two lanes between Avenue J and Six Flags Drive for SH 360 northbound mainline and frontage road construction. EXPECT DELAYS

SH 360 Northbound Mainlanes

  • Through Fall 2021: SH 360 northbound mainlanes will be temporarily shifted between Six Flags Drive and Avenue J onto the new SH 360 southbound mainline bridge. Click here to learn more.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Ave J/Lamar Boulevard/Six Flags Drive/Randol Mill Road

  • A new SH 360 southbound exit ramp to Avenue J/Lamar Boulevard is open to traffic.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard 

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Northbound Exit to Lamar Boulevard

  • Through Fall 2021: The SH 360 northbound exit to Lamar Boulevard will be closed for reconstruction. Traffic will be directed to exit Six Flags Drive and continue on the northbound frontage road to Lamar Boulevard

SH 360 Northbound Exit to I-30/Six Flags Drive/Lamar Boulevard/Avenue J

  • The SH 360 northbound exit to Six Flags Drive/Lamar Boulevard/Avenue J was moved to a new, temporary exit ramp. BE AWARE OF NEW TRAFFIC PATTERN. 

SH 360 Frontage Road

SH 360 Southbound Frontage Road

SH 360 South-to-North U-turn at Lamar Boulevard

  • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Six Flags Drive

  • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 Northbound Frontage Road

SH 360 North-to-South U-turn at Six Flags Drive

  • The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Lamar Boulevard

  • The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

Local Streets

Copeland Road

  • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
  • PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

105th Street

  • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.
Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects