SH 360 Entrance Ramp Closed at SP 303/Pioneer Parkway This Week
By Office of Communication
Posted on November 16, 2020, November 16, 2020

I-30 Detour Map

TxDOT is alerting drivers to a closure on SH 360. The northbound entrance ramp at SP 303/Pioneer Parkway will be closed through 6 a.m. Nov. 21, 2020. Traffic will be directed to the next entrance ramp at Park Row Drive.

New lane closures are planned for the next week as part of the $233 million Interstate 30/SH 360 Interchange Project and the SH 360 Widening Project. Closures are subject to changes due to weather and schedule. For more information, please visit the Keep 30360 Moving website.

 New or updated items are indicated in bold.

 The City of Arlington has partnered with Waze to give drivers the best experience possible to get around town. Drivers can download Waze for free at www.waze.com/get for iOS and Android and see real-time traffic, find optimal routes, avoid road closures and more.

Weekly Lane Closure Look Ahead

Closures are subject to changes due to weather and schedule. Below are anticipated traffic impacts for the coming weeks.

Click here to learn more about the I-30/SH 360 Interchange Project.

I-30 Mainlanes and Ramps 

I-30 Westbound Mainlanes

  • Through summer 2020: The right, outside auxiliary lane between Great Southwest Parkway to 0.2 miles east of Six Flags Drive exit ramp is closed for construction of new westbound exit ramp to Six Flags Drive.   

I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road

I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center Street and Duncan Perry Road

  • Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlanes and Ramps

SH 360 Southbound Mainlanes

  • Continuously through Fall 2021: SH 360 southbound mainlanes will be reduced to two lanes between Avenue J and Six Flags Drive for SH 360 northbound mainline and frontage road construction. EXPECT DELAYS.
  • Nightly through Nov. 24, 7 p.m. - 6 a.m.: Various lanes will be closed on SH 360 southbound mainlanes between Division Street and Kingswood Boulevard for general construction

SH 360 Northbound Mainlanes

  • Beginning Nov. 1: SH 360 northbound mainlanes will be temporarily shifted between Six Flags Drive and Avenue J onto the new SH 360 southbound mainline bridge. Click here to learn more.
  • Nightly through Nov. 24, 7 p.m. - 6 a.m.: Various lanes will be closed on SH 360 northbound mainlanes between Kingswood Boulevard and Division Street for general construction.

SH 360 Southbound Exit to I-30 Westbound

  • This direct connector ramp is now in service.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Ave J/Lamar Boulevard/Six Flags Dr./Randol Mill Road

  • A new SH 360 southbound exit ramp to Avenue J/Lamar Boulevard is open to traffic.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard 

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Northbound Exit to Lamar Boulevard

  • Through Fall 2021: The SH 360 northbound exit to Lamar Boulevard will be closed for reconstruction. Traffic will be directed to exit Six Flags Drive and continue on the northbound frontage road to Lamar Boulevard

SH 360 Southbound Entrance from Arkansas Lane

  • Daily, through Nov. 20, 9 a.m. - 3 p.m.: The SH 360 southbound entrance from Arkansas Lane will be closed for sound wall and traffic barrier construction. Traffic will be directed to the next entrance ramp from Mayfield Road

SH 360 Northbound Entrance from SP 303

  • Continuously through Nov. 21, 6 a.m.: The SH 360 northbound entrance from SP 303 will be closed for general construction. Traffic will be directed to the next entrance ramp from Park Row Drive.

    SH 360 Frontage Road

    SH 360 Southbound Frontage Road

    SH 360 South-to-North U-turn at Lamar Boulevard

    • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 South-to-North U-turn at Six Flags Drive

    • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 South-to-North U-Turn at Abram Street

    • Continuously through Nov. 30: The SH 360 south-to-north U-turn at Abram Street will be closed for SH 360 bridge work.

    SH 360 Northbound Frontage Road

    Mitchell Street to Prairie Oaks Boulevard
    •  Daily through Nov. 30, 9 a.m. - 3 p.m.: The left, inside lane of SH 360 northbound frontage road between Mitchell St to Prairie Oaks Blvd is closed for sound wall construction.
    Randol Mill Road to Avenue E
    • Continuous through Dec. 15: The SH 360 northbound frontage road between Randol Mill Road and Avenue E will be reduced to one lane for underground utility work.

    SH 360 North-to-South U-Turn at Abram Street

    • Continuously through Nov. 30: The SH 360 north-to-south U-turn at Abram Street will be closed for SH 360 bridgework.

    SH 360 North-to-South U-turn at Six Flags Drive

    • The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 North-to-South U-turn at Lamar Boulevard

    • The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    Local Streets

    Avenue F

    • Through fall 2020, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

    Copeland Road

    • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
    • PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

    Six Flags Drive

    • Continuously, Nov. 16-20: Westbound Six Flags Dr will be closed under SH 360 to place underground storm drainage. Traffic will be detoured north to cross at Lamar Blvd and return via the SH 360 southbound frontage road.
    • Continuously, Nov. 16-20: The eastbound Six Flags Drive left turn to the SH 360 northbound frontage road will be reduced to one lane for drainage work.

    Avenue E

    • Daily, Nov. 16-18, 9 a.m. - 3 p.m.: The left, inside lane of Avenue E eastbound and westbound between 106th and 107th Streets will be closed for intersection construction.

    Convention Center Drive/Copeland Road Intersection 

    • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

    105th Street

    • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.
    Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects